January:
Yes!! Finally, the construction of our new business premises has started. Immediately after the holidays and the new year, the contractor started with the groundwork and the contours for the foundation. The first utility pipes and the concrete mesh have already been installed, now we have to wait for the right temperatures to pour the concrete.
On to the next phase.
February:
Fase 1
During the first days of February, all concrete foundations were poured and prepared for the steel construction. The new building is quickly starting to take shape. The first part of the warehouse is already in place and the partition wall towards the office area has been installed. As can be seen, large windows will be installed between the warehouse and the rest for a spacious feeling and to allow ambient light to enter the entire building.
February:
Fase 2
The other (steel) construction has also been installed, and the building is increasingly taking on its final contours. A total of 71 tons of steel has been processed, with trusses of up to 25 meters long. The floors for the office area, canteen and experience center have also been lifted into place.
We will keep you informed of the developments in the near future!
ProCleanroom: Build your expertise.